The batteries are installed only by qualified service technicians. Installation time is dependent on the system design and size of the installation. 

The typical schedule of events: 

  • Unloading, erection, levelling
  • Filling tanks with electrolyte and first charge
  • Test of the hydraulic and electrical systems
  • Test of the remote communications
  • Electrical connection to the energy sources and loads
  • Test of the whole system and transfer to the customer